Causes of Early Age Cracking on Concrete Bridge Deck Expansion Joint Repair Sections

Table 1

Temperature and shrinkage steel calculations for bridge decks.

Job numberBridge numberDirectionBar area/foot of deck (in2/ft)ACI temperature/shrinkage (in2/ft)LRFD temperature/shrinkage (in2/ft)

11Westbound Pier 11.4480.0270.072
11Westbound Pier 21.4480.0270.072
11Westbound Pier 31.4480.0270.072
11Eastbound Pier 11.4480.0290.076
11Eastbound Pier 21.4480.0290.076
11Eastbound Pier 31.4480.0290.076
12Westbound Pier 1 (span 1)1.4480.0310.072
12Westbound Pier 1 (span 2)1.4480.0290.068
12Westbound Pier 2 (span 3)1.4480.0310.072
12Westbound Pier 2 (Span 2)1.4480.0290.068
12Eastbound Pier 1 (span 1)1.4480.0290.068
12Eastbound Pier 1 (span 2)1.4480.0270.065
12Eastbound Pier 2 (span 3)1.4480.0290.068
12Eastbound Pier 2 (Span 2)1.4480.0270.065
21Westbound Pier 11.370.0310.085
21Westbound Pier 21.370.0310.085
21Eastbound Pier 11.370.0310.085
21Eastbound Pier 21.370.0310.085
22Westbound Pier 11.4480.0290.076
22Westbound Pier 21.4480.0290.076
22Eastbound Pier 11.4480.0270.072
22Eastbound Pier 21.4480.0270.072
23Westbound Pier 1 (Span 1)1.6960.0290.068
23Westbound Pier 1 (Span 2)1.6960.0270.065
23Westbound Pier 2 (Span 2)1.4480.0270.065
23Westbound Pier 2 (Span 3)1.4480.0290.068
23Eastbound Pier 1 (Span 1)1.6960.0310.072
23Eastbound Pier 1 (Span 2)1.6960.0270.065
23Eastbound Pier 2 (Span 2)1.6960.0270.065
23Eastbound Pier 2 (Span 3)1.6960.0290.068
31Eastbound Pier 1 (Span 1)1.3330.0310.07
31Eastbound Pier 2 (Span 1)1.3330.0310.07
32Pier 1 (Span 1)1.5650.0330.072
32Pier 1 (Span 2)1.5650.0320.069
32Pier 2 (Span 2)1.5650.0320.069
32Pier 2 (Span 3)1.5650.0330.072
33Pier 1 (Span 1)1.5650.0330.072
33Pier 1 (Span 2)1.5650.0320.069
33Pier 2 (Span 2)1.5650.0320.069
33Pier 2 (Span 3)1.5650.0330.072
34Pier 1 (Span 1)1.5650.0350.075
34Pier 1 (Span 2)1.5650.0330.072
34Pier 2 (Span 2)1.5650.0330.072
34Pier 2 (Span 3)1.5650.0350.075