Aboveground tree biomass accumulated at 12, 24, and 36 months after planting.

TreatmentBiomass (Mg ha−1)
LeafBarkWoodBranchTotal

12 months

Control1.1b0.6b3.2C1.5b6.5c
Mineral fertilizer1.4b1.1a7.0b2.3a11.8b
Wet sewage2.6a1.2a7.8ab2.3a13.9ab
Dry sewage2.9a1.3a9.2a2.6a15.9a

24 months

Control4.1b2.4b13.2b4.3b24.0b
Mineral fertilizer7.2a4.8a34.5a8.0a54.6a
Wet sewage7.4a4.4a31.1a7.4a50.3a
Dry sewage8.6a5.3a37.6a8.8a60.3a

36 months

Control2.1c4.2c41.4C4.0c51.7C
Mineral fertilizer3.9a b6.6b76.8a b6.0a b93.3a b
Wet sewage3.6b6.5b71.3b5.7b87.2B
Dry sewage4.4a8.0a87.5a6.6a106.5A

Significant differences ( ) among treatments at a given age are indicated by different letters in the same column.