Upscaling of an Innovative Cogeneration CSP System
Table 2
Economic input data and assumptions.
| Scenario | Specific capital cost (€/kWe) | Fixed O&M (€/kWe/month) | Variable O&M (€/MWh) |
| CCGT base case | 1154 | 2.58 | 1.78 | CCGT low NG cost | 1154 | 2.58 | 1.78 | CSP-DSW 5 MWe | 6337 | 10.56 | 0.46 | CSP-DSW 10 MWe | 6093 | 10.16 | 1.02 | CSP-DSW 25 MWe | 5844 | 9.74 | 1.59 | CSP-DSW 50 MWe | 5752 | 9.59 | 1.80 |
|
|