Discrete Dynamics in Nature and Society
Volume 2014 (2014), Article ID 917685, 7 pages
http://dx.doi.org/10.1155/2014/917685
Research Article

A Constraint Programming Method for Advanced Planning and Scheduling System with Multilevel Structured Products

1School of Management, Shanghai University, Shanghai 200444, China
2Wenzhou University, Wenzhou, Zhejiang 325035, China

Received 5 July 2013; Revised 6 November 2013; Accepted 3 December 2013; Published 2 January 2014

Academic Editor: Tinggui Chen

Copyright © 2014 Yunfang Peng et al. This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

Linked References

  1. K. Sheikh, Manufacturing Resource Planning (MPR II) with an Introduction to ERP, SCM, and MRP, McGraw-Hill, New York, NY, USA, 2003.
  2. Advanced Planning and Scheduling in High Tech industry. A Eyeon white paper.
  3. H. Stadtlere and C. Kilger, Supply Chain Management and Advanced Planning: Concepts, Models, Software and Case Studies, Springer, Berlin, Germany, 3rd edition, 2005.
  4. L.-C. Kung and C.-C. Chern, “Heuristic factory planning algorithm for advanced planning and scheduling,” Computers and Operations Research, vol. 36, no. 9, pp. 2513–2530, 2009. View at Publisher · View at Google Scholar · View at Scopus
  5. C. Moon, J. S. Kim, and M. Gen, “Advanced planning and scheduling based on precedence and resource constraints for e-plant chains,” International Journal of Production Research, vol. 42, no. 15, pp. 2941–2954, 2004. View at Publisher · View at Google Scholar · View at Scopus
  6. K. J. Chen and P. Ji, “A mixed integer programming model for advanced planning and scheduling (APS),” European Journal of Operational Research, vol. 181, no. 1, pp. 515–522, 2007. View at Publisher · View at Google Scholar · View at Zentralblatt MATH · View at MathSciNet
  7. A. Örnek, S. Özpeynirci, and C. Öztürk, “A note on ‘A mixed integer programming model for advanced planning and scheduling (APS)’,” European Journal of Operational Research, vol. 203, no. 3, pp. 784–785, 2010. View at Publisher · View at Google Scholar · View at MathSciNet
  8. C. Öztürk and A. M. Ornek, “Operational extended model formulations for advanced planning and scheduling systems,” Applied Mathematical Modelling, vol. 38, no. 1, pp. 181–195, 2014. View at Publisher · View at Google Scholar · View at MathSciNet
  9. S. Kreipl and M. Pinedo, “Planning and scheduling in supply chains: an overview of issues in practice,” Production and Operations Management, vol. 13, no. 1, pp. 77–92, 2004. View at Scopus
  10. Y. Chen, Z. Guan, Y. Peng, X. Shao, and M. Hasseb, “Technology and system of constraint programming for industry production scheduling. Part I: a brief survey and potential directions,” Frontiers of Mechanical Engineering in China, vol. 5, no. 4, pp. 455–464, 2010. View at Publisher · View at Google Scholar · View at Scopus
  11. S. Topaloglu, L. Salum, and A. A. Supciller, “Rule-based modeling and constraint programming based solution of the assembly line balancing problem,” Expert Systems with Applications, vol. 39, no. 3, pp. 3484–3493, 2012. View at Publisher · View at Google Scholar · View at Scopus
  12. H.-H. Hvolby and K. Steger-Jensen, “Technical and industrial issues of advanced planning and scheduling (APS) systems,” Computers in Industry, vol. 61, no. 9, pp. 845–851, 2010. View at Publisher · View at Google Scholar · View at Scopus
  13. K. Steger-Jensen, H.-H. Hvolby, P. Nielsen, and I. Nielsen, “Advanced planning and scheduling technology,” Production Planning and Control, vol. 22, no. 8, pp. 800–808, 2011. View at Publisher · View at Google Scholar · View at Scopus
  14. Y.-S. Yun and M. Gen, “Advanced scheduling problem using constraint programming techniques in SCM environment,” Computers and Industrial Engineering, vol. 43, no. 1-2, pp. 213–229, 2002. View at Publisher · View at Google Scholar · View at Scopus
  15. L. J. Zeballos, O. D. Quiroga, and G. P. Henning, “A constraint programming model for the scheduling of flexible manufacturing systems with machine and tool limitations,” Engineering Applications of Artificial Intelligence, vol. 23, no. 2, pp. 229–248, 2010. View at Publisher · View at Google Scholar · View at Scopus
  16. F. Rossi and P. T. Walsh, Handbook of Constraint Programming, Elsevier, Amsterdam, The Netherlands, 2006.
  17. A. S. Jain and S. Meeran, “Deterministic job-shop scheduling: past, present and future,” European Journal of Operational Research, vol. 113, no. 2, pp. 390–434, 1999. View at Scopus
  18. C. Artigues and D. Feillet, “A branch and bound method for the job-shop problem with sequence-dependent setup times,” Annals of Operations Research, vol. 159, pp. 135–159, 2008. View at Publisher · View at Google Scholar · View at Zentralblatt MATH · View at MathSciNet