Abstract

Modern trams are developing fast because of their characteristics like medium capability and energy saving. Exclusive way is always set in practice to avoid interruption from general vehicles, while trams have to stop at intersections frequently due to signal rules in the road network. Therefore, signal optimization has great effects on operational efficiency of trams system. In this paper, an arterial signal coordination optimization model is proposed for trams progression based on the Asymmetrical Multi-BAND (AM-BAND) method. The AM-BAND is modified from the following aspects. Firstly, BAM-BAND is developed by supplementing active bandwidth constraints to AM-BAND. Assisted by the IBM ILOG CPLEX Optimization Studio, two arterial signals plans with eight intersections are achieved from AM-BAND and BAM-BAND for comparison. Secondly, based on the modified BAM-BAND, a BAM-TRAMBAND model is presented, which incorporates three constraints regarding tram operations, including dwell time at stations, active signal priority, and minimum bandwidth value. The case study and VISSIM simulation results show that travel times of trams decrease with signal plan from BAM-TRAMBAND comparing with the original signal plan. Moreover, traffic performance indicators such as stops and delay are improved significantly.

1. Introduction

Modern trams are medium capability urban public transit and develop fast in recent years of China for its characteristics of energy efficiency, environmental friendliness, and passenger comfort. As of 2015, trams are fully operated in nine cities with 180 km in total length which represents 5.1% of overall urban rail transit distance in China [1]. Unlike other rail transit modes with exclusive right-of-way such as metro, light rail, and maglev, trams operate in an open road network and they are frequently interrupted by other vehicles and have to observe signal rules. To improve operational efficiency, two countermeasures are usually employed.

On one hand, exclusive way is provided for trams to avoid interweaving with other vehicles. On the other hand, signal priority strategies are adopted to ensure trams passing through intersections orderly and safely. Active, passive, and adaptive approaches are three main priority strategies [2]. Active priority provides early green, green extend, phase insertion, and other countermeasures to create extra green time for trams when they approach intersection [3, 4]. However, this method interferes with the original timing and imposes delays on other vehicles to certain extent. Sometimes even conducting early green or green extend strategies trams still probably arrive during red time. Besides active priority, green-wave band, as a passive priority strategy, is provided for trams in Athens [5]. Arterial signal coordination can create green-wave band. If a tram travels in green bandwidth, it will pass through all the arterial intersections without stop. This is more meaningful for trams with exclusive way, since there is no interruption from other vehicles. Therefore, it is necessary to explore signal coordination model for trams.

Morgan and Little [6] and Little [7] proposed an arterial signal coordination method for motorcade to maximize bandwidth. They converted the signal problem to a mixed integer linear programing problem to attain uniform cycle, phase time, offset, and progression speed. Solution procedure utilizing branch-and-bound algorithm was provided in the study. In 1981, Little et al. [8] named this method MAXBAND and improved it by considering left-turn phase sequence and queue clearance time. Each band of the both-way green bands from MAXBAND owns the same width and is symmetrical along progression line. Having contracted by the Federal Highway Administration, the Texas Transportation Institute recognized that the left-turn phase sequence would be an important variable in multiarterial closed networks and proposed the MAXBAND-86 model [9]. Based on MAXBAND, Messer et al. [10], Chang and Messer [11], and Chaudhary and Messer [12] developed a series of PASSER programs to optimize arterial signal timing. In addition, Cohen [13] and Cohen and Mekemson [14] combined MAXBAND with TRANSYT (Traffic Network Study Tool). They used the bandwidth-based program MAXBAND to select proper left-turn phase sequence subsequently, followed by delay-based program TRANSYT to determine the final offsets. The resulting signal timing plan had lower delay than either class of programs individually.

For improving the utilization of green time, Gartner et al. [15, 16] relaxed the same band constraints along the progression line and presented a multiband method, which is the MULTIBAND model. Stamatiadis and Gartner [17] and Gartner and Stamatiadis [18] then realized its application in multiarterial traffic networks. Even though MULTIBAND relaxes the same band constraints, there is still a part of available band which cannot be utilized. In 2015, Zhang et al. [19] proposed an asymmetrical and multiband model named AM-BAND which relaxed the symmetrical constraints in MULTIBAND further. This model increases bandwidth and decreases the stops and delay of motorcades.

There is a gradual evolutionary relationship among MAXBAND, MULTIBAND, and AM-BAND. The schematic bandwidth results of the three models are shown in Figure 1. Although they widen the bandwidth, there is inactive area in the results. A certain band area is always left unused.

MAXBAND is designed for solving arterial signal coordination for general vehicles, but it is not entirely suitable for public transits because there is no time for stopping at stations in the bandwidth. Jeong and Kim [20, 21] modeled TRAMBAND by considering stops at stations for trams based on MAXBAND. Two both-way bandwidths for trams and general vehicles were achieved concurrently. Stops and delay at intersections for trams decreased from TRAMBAND compared with MAXBAND, while general vehicles delay increased slightly. Similarly, Dai et al. [22] introduced Model for bus green band, Model for general vehicles band, and Model for both green bands. Furthermore, Dai et al. [23] categorized intersections along the arterial according to the locations of bus stops. Models were then developed by optimizing the bandwidth for each group of intersections and connecting the central lines of green bands for adjacent groups. The both-way bandwidths for buses were obtained and bandwidths for different groups were not necessarily the same.

Most signal coordination methods for public transits are developed on the basis of MAXBAND, and they introduce constraints on stops at stations. These methods are clearly based on passive priority strategy. In fact, active priority and passive priority approaches are not in conflict. After a passive priority solution is confirmed, active priority is conducted for supplementing, which can enhance operation efficiency of trams and ensure smooth intersection passage without stop. Wang et al. [24] developed a double-level system for bus priority. The upper level was progression control. Cycle, green band, and offset were optimized according to the data of general vehicles from detectors. The lower level was bus priority control. Green extended and early start modes were adopted to achieve bus signal priority with respect to the upper level results for signal coordination. However, the existing arterial signal coordination model was only utilized but not optimized. Arterial signal coordination and actuated signal control are still two separate methods.

It should be specially mentioned that there are some researches that criticized classical traffic flow theories including green-wave theory. Kerner [25, 26] holds the view that green-wave breakdown occurred when the moving synchronized flow patterns propagated within the green-wave, and then the moving synchronized flow patterns transformed into a moving queue. It has to admit that three-phase traffic flow and queue problems indeed influence the effectiveness of MAXBAND in reality. However, trams’ travelling characters and environment are different from general vehicles. On one hand, exclusive lane and its discrete arriving help to avoid trams’ breakdown. On the other hand, compared with motorcade, it is easier to control the stopping, accelerating, decelerating, and speed of trams artificially or automatically according to the train diagram. Therefore, the modified model can be used better for trams.

Based on the literatures review above, an arterial signal coordination optimization model for trams is proposed by modifying AM-BAND in the following aspects:(i)Active bandwidth: incorporate active bandwidth constraints.(ii)Dwell time: incorporate constraints of trams’ dwell time at station.(iii)Active priority: provide early green and green extend signal priority strategies for trams at the intersection.(iv)Minimum bandwidth: introduce minimum bandwidth value constraints to consider long tram body length.

The modified model with the active bandwidth constraint (i) is named BAM-BAND. The model with constraints (ii), (iii), and (iv) based on BAM-BAND is denoted as BAM-TRAMBAND. These two new models are still mixed integer linear programing problems. The remainder of this paper is organized as follows. Section 2 introduces the AM-BAND approach and discusses the results of an example. The bandwidth area is developed firstly in Section 3 and BAM-BAND is then proposed by introducing the active band bandwidth constraints. Finally in this section, the optimization model for trams, BAM-TRAMBAND, is proposed with constraints of dwell time, active priority, and minimum bandwidth. In Section 4, a case study and simulation analysis are conducted with the BAM-TRAMBAND approach and VISSIM software.

2. AM-BAND Model and Application

2.1. AM-BAND Model

AM-BAND model is an arterial signal coordination approach which falls in the category of passive priority. Signal timings of all intersections are fixed timing schemes. There are both green bands for two travel directions along the arterial including outbound and inbound as described in Figure 2.

The objective function of AM-BAND, as defined in (1), is to maximize weighted sum of bandwidths of outbound and inbound. Outbound bandwidth and inbound bandwidth are composed of left and right parts, and and and , which implies the green band of AM-BAND in each segment is asymmetrical and multiband. Constraints are (2)~(11). The decision variables include , , , , , , , , , , , and :

Constraint (2) allows the arterial direction with a higher traffic volume to enjoy a wider progression band. Constraint (3) defines the lower and upper limits of cycle length. Two reciprocals are used here so that the remaining constraints can be expressed in linear form and solved by mixed integer linear programing. Constraint (4) is an interference constraint which ensures left and right boundaries do not interfere with the corresponding edges of red signals, respectively. Constraint (5) ensures that the left or right part of a progression band is nonzero. Constraint (6) is the well-known loop integer constraint. It releases the relationship among signal timing, bandwidth, and travelling speed. Values combinations of and represent left-turn phase sequence. The optimal timing plan on straight and left-turn can be obtained from zero/one variables and and left-turn green time . Constraints (7) and (8) impose upper and lower limits on the travel speed of each segment and the speed change between consecutive segments. Left constraints (9), (10), and (11) are domains of definition.

The AM-BAND model consists of constraints and variables. For more details about AM-BAND model see [19]. The notations and parameters used are explained in Notations. Some of their units are converted into cycles for mixed integer linear form.

2.2. Example Application for AM-BAND Model

For illustrating how it works and as the comparison results later, an arterial with eight intersections, as shown in Figure 3, is employed in this example. Lower and upper limits on cycle length are 70 s and 100 s. Results from AM-BAND are illustrated in Table 1. The optimization cycle is 70 s, weighted sum of bandwidths is 426 s, and average bandwidth is 30.4 s. Time-space diagram of green band is given in Figure 4.

3. Arterial Signal Coordination Optimization Model for Tram

The optimization model is developed by modifying AM-BAND in two steps. Firstly, the active bandwidth area is defined and the BAM-BAND is constructed by supplementing active bandwidth constraints to AM-BAND. Secondly, with the consideration of dwell time, active priority, and minimum bandwidth constraints, an arterial signal coordination optimization model BAM-TRAMBAND for trams is developed.

3.1. Active Bandwidth Area

Although AM-BAND gives asymmetrical and multiband results to increase band’s width, while not the entire bandwidth is active, it has been found that some of the bandwidth is always left unused. Because bandwidth is various, the bandwidth area as the relative availability can be indicated. In this study, bandwidth area refers to the sum of bandwidth values of each segment along the arterial multiplied by the matching distance between two intersections, as expressed in (12). The bandwidth area of the case in Section 2.2 from AM-BAND is 189880 m·s; thus  m·s:

The active bandwidth area is the part of which is available, while the inactive bandwidth area is the left part which is not available regardless of how the vehicles progress at reasonable speed. The inactive bandwidth area can be explained by intercepting the time-space diagram from to of green band. In Figure 5, if the left band in the outbound direction broadens, namely, , there appears area which cannot be used even if the vehicle proceeds at maximum speed. Similarly, if the right band in outbound direction narrows, namely, , once vehicle drives into the shadow area near to the right boundary, it will encounter red light at the next intersection even on full speed and overstep green band. Therefore, although bandwidth area from AM-BAND is 189880 m·s, not the entire area is effective. Its active bandwidth area m·s and inactive bandwidth area  m·s. The active bandwidth area rate , which indicates just 81% of the bandwidth area is available from AM-BAND for the case.

3.2. BAM-BAND Model

From the above discussion, there is inactive bandwidth area when left band broadens or right band narrows along the outbound direction. Similarly, if left band narrows or right band broadens along the inbound direction, inactive bandwidth area exists. Thus, active bandwidth constraints are necessary to eliminate invalid bandwidth. Active bandwidth constraints (13) beyond AM-BAND are introduced in the optimization model and thus the BAM-BAND model:

The case study in Section 2.2 is then solved by BAM-BAND and results from these two models are listed in Table 2. The optimization cycle is 75 s. Weighted sum of bandwidths from BAM-BAND decreases by 7% and bandwidth area drops by 8% compared with AM-BAND, while active bandwidth area increases by 13%. For the purpose of comparison, the cycle time is fixed at 70 s. In this condition, weighted sum of bandwidths from BAM-BAND reduces by 14%, and bandwidth area drops 15%, while active bandwidth area improves 5%. In addition, travel times of outbound and inbound save 9% and 14%, respectively. These results prove that even though calculated bandwidth is smaller derived from BAM-BAND, the available bandwidth is in fact larger.

3.3. BAM-TRAMBAND Model

To extend this arterial signal coordination optimization model to trams, another three constraints including dwell time, active priority, and minimum bandwidth are introduced.

(1) Dwell Time Constraints. Dwell time constraints arewhere denotes dwell time of outbound (inbound); denotes the minimum dwell time of outbound (inbound) ensuring boarding and alighting time of passengers; denotes the maximum dwell time of outbound (inbound) allowed. Dwell time is usually determined according to passenger numbers boarding and alighting at each station [27]. Moreover, travel speed and speed change constraints (15) and (16) replace (8) and (9), where is zero/one variable. If there is a station in segment , it equals 1. Otherwise, it equals 0. Consider

(2) Active Priority Strategies. Arterial signal coordination is a passive priority approach. All signal timings are fixed. As the wave of travelling speed and deviation of dwell time at stations, trams are likely to miss the green band. It is possible to combine the advantages from active priority strategies, like early green and green extend, and that from passive priority.

Constraint (17) is adopted to replace (4). denotes the maximum early green time and denotes the maximum green extend time for trams. These two values should not be too large to avoid causing excessive delay to vehicles in other phases [28]. Consider

(3) Minimum Bandwidth Constraints. The tram body length is quite long, ranges from 20 m to 50 m. The bandwidth should be sufficiently wide for passing of the whole body. Objective function of optimization model is to maximize weighted sum of bandwidths, but there is a lack of requirement for bandwidth in each segment. As a consequence, bandwidth in some segments may be very small even if the objective function value is maximized. Constraint (18) is then required to ensure the minimum bandwidth. The minimum bandwidth value can be determined according to tram body length:

BAM-TRAMBAND is now completed and it is still a mixed integer linear programing problem. Constraints are (2), (3), (5), (6), (9)~(11), and (13)~(18). There are constraints and variables in the model.

4. Case Study and Simulation Analysis

The example in Section 2.2 is further analyzed in this case study. Four tram stations are set between intersections 1 and 2, 3 and 4, 5 and 6, and 6 and 7. And there is exclusive way for trams. The problem is modeled by BAM-TRAMBAND and the solution is calculated by IBM ILOG CPLEX Optimization Studio.

The optimization cycle is 80 s, weighted sum of bandwidths is 445 s, and average bandwidth is 31.8 s. Other results are given in Table 3. Time-space diagram of green band is shown in Figure 6.

An arterial with eight intersections and four stations according to the case is constructed in VISSIM simulation platform. The original timing plan and signal coordination optimization plan are simulated, respectively, with the period of 6 hours. The results under these two timing plans are obtained for comparison. Relevant results of general vehicles and trams are listed in Table 4.

Table 4 shows that, with the arterial signal coordination optimization plan from BAM-TRAMBAND, 12% and 20% of travel times of trams in two directions are saved, respectively, and standard deviations decrease almost by half. Under the original timing plan, trams stop more than 4 times at intersections, which indicates they meet red light at half of the intersections. The signal delay reaches 100 s in total. Under the optimization timing plan, trams pass through all these eight intersections without stop. Therefore, BAM-TRAMBAND is effective for arterial signal coordination optimization and enhancing operation efficiency of trams.

Stop frequency and delay of general vehicles reduce slightly. This is because arterial signal coordination method only arranges phase sequences instead of changing the green time. Original timing cycle of each intersection ranges from 70 s to 100 s. The optimization cycle is 80 s. For those unsaturated intersections whose cycle lengths are longer than 80 s before optimization, the optimization timing decreases their cycle time. This is helpful to reduce signal delay to some degree.

5. Conclusions

In this paper, an arterial signal coordination optimization model is proposed for trams based on the AM-BAND method. The modified method makes two main improvements. The BAM-BAND and BAM-TRAMBAND models are proposed accordingly.

AM-BAND is an asymmetrical and multiband method. It relaxes the symmetrical progression band requirement in the well-known MULTIBAND model. The bandwidth is allowed to be larger in AM-BAND, because it is not necessarily symmetrical with respect to the progression line. It is found in this study that if the left band broadens or the right band narrows along outbound direction or the left band narrows or the right band broadens along inbound direction, a significant inactive bandwidth area may be exist.

BAM-BAND is developed by incorporating active bandwidth constraints into AM-BAND. It prevents the left band from broadening and the right band from narrowing along the outbound direction and the left band from narrowing and the right band from broadening along the inbound direction. Results obtained from BAM-BAND indicate fully active bandwidth. Even though bandwidth reduces 15% from BAM-BAND compared with AM-BAND under the same conditions, active bandwidth area increases by 5%. Available bandwidth area for vehicle becomes larger with the modified model.

There are stops at stations for trams. Active priority strategies can be adopted to ensure trams progression without stop at intersections, in addition to passive priority approach. Minimum bandwidth is necessary for trams because of long body length. BAM-TRAMBAND is then proposed by adding dwell time, active priority, and minimum bandwidth constraints to BAM-BAND. With BAM-TRAMBAND, travel times of trams in two directions are reduced by 12% and 20%, respectively, compared with the original timing plan. Stops and delay at intersections drop to zero. BAM-TRAMBAND is able to develop efficient priority and improve service quality.

In the future, researches can be conducted from several aspects. Firstly, the signal coordination model discussed in this paper is only for one arterial. So, signal timings in the tram networks with interlaced lines are also worthy of studying. Secondly, one of trams’ peculiarities is the limitation of timetable. To respect the operation schedule, timetable should be also considered when making signal coordination plans. Lastly, trams progression model is being developed to consider the influence of station’s location such as near-side, far-side, and mid-block.

Notations

Sets
:Set of intersections.
Indices
:Number of intersections in the arterial
:Index of intersection and segment, .
Parameters
:Link specific weights in the two directions, where and
:Outbound (inbound) total directional volume (pcu/h)
:Outbound (inbound) saturation flow (pcu/h)
:Exponential power whose values are 0, 1, 2, and 4 usually used
:Target ratios of inbound to outbound bandwidth on section ; if ,
and :Upper and lower limits on cycle length (s)
:Outbound (inbound) queue clearance time at (cycles)
:Outbound (inbound) red time at (cycles)
:Can be any positive real number (e.g., )
:Time allocated for outbound (inbound) left-turn green at (cycles)
:Outbound (inbound) green time for through traffic at (cycles)
:Distance between and outbound (inbound) (m)
:Lower/upper limits on outbound (inbound) speed (m/s)
:Lower/upper limits on change in outbound (inbound) speed (m/s).
Intermediate Variables
:Weighted sum of bandwidth of outbound and inbound; average of it is (cycles)
:Travel speed of outbound from to , travel speed of inbound from to (m/s)
:Internode offsets (cycles)
:Intranode offset, which is the time difference between the center of and the nearest center of ; it is positive if the center of is to the right of the center of (cycles).
Decision Variable
:Outbound (inbound) bandwidth for segment (cycles)
:Signal frequency, , where is signal cycle (cycles/s)
:Interference variable; it equals time from right (left) side of red at to left (right) edge of outbound (inbound) green band (cycles)
:Travel time from to outbound [ to inbound] (cycles)
:0-1 variables to determine the left-turn pattern
:Loop integer variable.

Competing Interests

The authors declare that there are no competing interests regarding the publication of this paper.

Acknowledgments

This research was funded by the Fundamental Research Funds for the Central Universities (2015YJS090), the National Basic Research Program of China (no. 2012CB725406), and the National Natural Science Foundation of China (NSFC) (no. 71390332).