An Overview of Recent Research Results and Future Research Avenues Using Simulation Studies in Project Management

Table 1

The MAPE for the three methods along the completion stage and network structure (Source [4]).

ā€‰ Early stage Middle stage Late stage
ā€‰P S/P S P S/P S P S/P S

PVM 12.30% 13.69% 14.07% 9.91% 9.88% 8.50% 12.08% 9.48% 7.32%
EDM 12.30% 13.69% 14.07% 9.91% 9.90% 8.51% 7.73% 5.52% 3.96%
ESM 10.40% 8.59% 8.22% 7.84% 4.96% 3.76% 4.05% 1.94% 1.31%