Construction stages and time.
| Filling step | Time | Remark |
| ① | 1996.01–1996.06 | Fill dam body | ② | 1996.07–1997.02 | Fill dam body | ③ | 1997.03–1997.05 | Cast Phase 1 concrete slab | ④ and ⑥ | 1997.02–1997.10 | Fill dam body | ⑤ |
1997.05-1997.05 | Water level rises | ⑦ | 1997.06–1997.10 | Water level fluctuation | ⑧ and ⑨ | 1997.11–1998.01 | Fill dam body | ⑩ | 1997.12–1998.05 | Cast Phase 2 concrete slab | ⑪ | 1997.11-1997.12 | Water level rises | ⑫ | 1998.02–1998.08 | Fill dam body | ⑬ | 1998.06-1998.07 | Water level rises | ⑭ | 1998.08–1999.01 | Fill dam body | ⑮ | 1999.01–1999.05 | Cast Phase 3 concrete slab | ⑯ | 1999.06–1999.09 | Store water |
|
|