Construction stages and time.

Filling stepTimeRemark

1996.01–1996.06Fill dam body
1996.07–1997.02Fill dam body
1997.03–1997.05Cast Phase 1 concrete slab
and 1997.02–1997.10Fill dam body
1997.05-1997.05Water level rises
1997.06–1997.10Water level fluctuation
and 1997.11–1998.01Fill dam body
1997.12–1998.05Cast Phase 2 concrete slab
1997.11-1997.12Water level rises
1998.02–1998.08Fill dam body
1998.06-1998.07Water level rises
1998.08–1999.01Fill dam body
1999.01–1999.05Cast Phase 3 concrete slab
1999.06–1999.09Store water