Multiproject Resources Allocation Model under Fuzzy Random Environment and Its Application to Industrial Equipment Installation Engineering

Table 4

An optimal resource assignment scheme after 20 experiments.

Assign methodsā€‚Total cost
(unit: T RMB)
Finishing time Actual usage Total resource
transfers
Project 1Project 2 Project 3

BLOAM 5242 September 6 November 16 September 25 96.42% 224
SWAM 6381 September 6November 16 September 25 78.38% 136
FISFS 5768 September 6November 24 October 1592.13%248
MINPDD 5966 September 6November 24 October 1594.35%236
MINPSLK 5842 September 26 November 24 September 2889.72%198