Research Article
Magnitude of Construction Cost and Schedule Overruns in Public Work Projects
Table 10
ANOVA results, construction cost and schedule overruns by project duration.
| Project construction duration | Unit | Mean | -value | -value | -critical |
| Construction cost overrun | | | Less than 1 year | % | 2.46 | 6.853 | 0.009** | 3.867 | More than 1 year | % | 4.59 | Construction schedule overrun | | | Less than 1 year | % | −4.56 | 37.585 | <0.001** | 3.867 | More than 1 year | % | 21.79 |
|
|
Statistically significant at alpha level 0.05. Statistically significant at alpha level 0.01.
|