Magnitude of Construction Cost and Schedule Overruns in Public Work Projects

Table 10

ANOVA results, construction cost and schedule overruns by project duration.

Project construction durationUnitMean -value -value -critical

Construction cost overrun
 Less than 1 year%2.466.8530.009**3.867
 More than 1 year%4.59
Construction schedule overrun
 Less than 1 year%−4.5637.585<0.001**3.867
 More than 1 year%21.79

Statistically significant at alpha level 0.05.
Statistically significant at alpha level 0.01.