Research Article

Magnitude of Construction Cost and Schedule Overruns in Public Work Projects

Table 11

ANOVA results for construction cost and schedule overruns by project completion year.

Project completion yearUnitMean -value -value -critical

Construction cost overrun
 From 1991 to 2000%2.660.7210.3963.867
  From 2001 to 2008%3.25
Construction schedule overrun
 Less than 1 year%4.232.0930.1493.867
 More than 1 year%−1.27