Magnitude of Construction Cost and Schedule Overruns in Public Work Projects

Table 6

Test of homogeneity.

MetricsLevene’s statisticSignificance

Factor: project types
 Construction cost overrun3.1170.045
 Construction schedule overrun0.1750.840
Factor: project size
 Construction cost overrun1.8190.164
 Construction schedule overrun12.203 <0.001**
Factor: project construction duration
 Construction cost overrun2.8710.091
 Construction schedule overrun11.1740.001**
Factor: project completion year
 Construction cost overrun0.7810.377
 Construction schedule overrun10.7560.001**

Statistically significant at alpha level 0.05.
Statistically significant at alpha level 0.01.