Magnitude of Construction Cost and Schedule Overruns in Public Work Projects

Table 8

ANOVA results, construction cost and schedule overruns by project size.

Project typesUnitMean -value -value -critical

Construction cost overrun
 Less than $1 million%1.674.2120.016*3.020
 $1 million to $5 million%3.55
 Greater than $5 million%3.92
Construction schedule overrun
Less than $1 million%−11.2316.538<0.001**3.020
 $1 million to $5 million%4.99
 Greater than $5 million %14.35

Statistically significant at alpha level 0.05.
Statistically significant at alpha level 0.01.