Magnitude of Construction Cost and Schedule Overruns in Public Work Projects
Table 9
Post hoc analysis for construction cost and schedule overruns by project size.
| Project size | Less than $1 M | $1 M to < $5 M | Greater than $5 M | Mean difference | value | Mean difference | value | Mean difference | value |
| Construction cost overrun | | | | | | | Less than $1 million | — | — | 1.88 | 0.054 | 2.26 | 0.026* | $1–$5 million | 1.88 | 0.054 | — | — | 0.38 | 0.902 | Greater than $5 million | 2.26 | 0.026* | 0.38 | 0.902 | — | — | Construction schedule overrun | | | | | | | Less than $1 million | — | — | 16.23 | 0.001** | 25.59 | <0.001** | $1–$5 million | 16.23 | 0.001** | — | — | 9.36 | 0.109 | Greater than $5 million | 25.59 | <0.001** | 9.36 | 0.109 | — | — |
|
|
Statistically significant at alpha level 0.05. Statistically significant at alpha level 0.01.
|