Magnitude of Construction Cost and Schedule Overruns in Public Work Projects

Table 9

Post hoc analysis for construction cost and schedule overruns by project size.

Project sizeLess than $1 M$1 M to < $5 MGreater than $5 M
Mean difference valueMean difference valueMean difference value

Construction cost overrun
 Less than $1 million1.880.0542.260.026*
 $1–$5 million1.880.0540.380.902
 Greater than $5 million 2.260.026*0.380.902
Construction schedule overrun
 Less than $1 million16.230.001**25.59<0.001**
 $1–$5 million16.230.001**9.360.109
 Greater than $5 million25.59<0.001**9.360.109

Statistically significant at alpha level 0.05.
Statistically significant at alpha level 0.01.