Research Article
A Novel Resource-Leveling Approach for Construction Project Based on Differential Evolution
Table 5
Result comparison.
| Approach | Performance | | | RVmax | CRV |
| Early start schedule | 15339 | 28 | 13 | 151 | Microsoft Project 2007 | 15245 | 24 | 12 | 139 | PSO | 13965 | 20 | 7 | 72 | GA | 13945 | 21 | 7 | 95 | RLDE | 13839 | 19 | 7 | 57 |
|
|