Research Article
Identification and Classification of the Unique Features of Mass Housing Projects
Table 3
Mean score results on the attributes.
| S/No. | Features | Mean | Std. deviation | Std. error mean | Remarks |
| 1 | Multiple site for various units | 4.42 | .554 | .099 | Accepted | 2 | Multiple standardized design-units in scheme | 4.28 | .615 | .112 | Accepted | 3 | Multiple environmental impact | 1.83
*
| .811 | .169 | Rejected | 4 | Multiple geographical location for schemes | 4.06 | .715 | .131 | Accepted | 5 | Multiple interdependent subcontracting under scheme | 4.22 | .637 | .117 | Accepted | 6 | Multiple one-off infrastructure | 1.64
*
| .961 | .141 | Rejected | 7 | Complex network of procurement systems | 3.78 | .681 | .149 | Accepted | 8 | Multicollinear repeated preliminary activities on units | 4.39 | .549 | .096 | Accepted | 9 | Repetitive tasks on standardized units | 4.14 | .639 | .117 | Accepted | 10 | Virtual team participants | 4.17 | .655 | .677 | Accepted | 11 | Complex construction method | 1.67
*
| .894 | .100 | Rejected | 12 | Complex network of risk from various units | 1.72
*
| .815 | .156 | Rejected | 13 | Complex network of team relationship | 4.44 | .558 | .139 | Accepted | 14 | Multiple duration for units under schemes | 4.03 | .654 | .114 | Accepted |
|
|
Source: field data (*mean scores less than 3.5).
|