Prioritization of risk group | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
|
1 | Economic factors | Inflation | Annual budget revision | Currency change rate | Contractors financial failures | Economical instability | Investment problems | | | | | | | | |
|
2 | Project management | Change in managerial methods | Losing experienced staffs | Inappropriate project team | Not to assign tasks to experienced staff | Inappropriate goals and objectives definitions | Rush at auction | | | | | | | | |
|
3 | Partners | Interference by the owner | Delay of consultants | Delay in decision-making (owner) | Delay in payment to contractors | Challenges between stakeholders | Lack of consultant knowledge on terms and conditions | Method of tendering and vendor selection | Poor communication between project parties | Lack of mediators to solve problems | Contractors delay | Contractors mismanagement | Weak workshop management | Contractors lack of experience | Contractor financial power |
|
4 | Execution | Delays in executive plan confirmation | Delayed, incomplete, and incorrect reviews | Project closure | Permits and licenses | Events during execution | Deviations between spec. and implementation | Inappropriate material and instruments | Environmental instability | Damage to property and persons | Landslides | | | | |
|
5 | Human resources | Human resources turnover | Lack of specialists | | | | | | | | | | | | |
|
6 |
Political | Sanction | Governmental changes | Change in governmental rules | War | | | | | | | | | | |
|
7 | Legal factors | Legal disputes | Change in negotiation trend | Delays in payments | Delays in resolving disputes | Lack of moderator | | | | | | | | | |
|
8 |
Environmental and social | Rules changes | Ambiguity in the rules | Strike | Environmental risks | | | | | | | | | | |
|
9 | Resources and equipment | Changes in materials during construction | Delay in material supply | Lack of machines and equipment | Equipment performance | Supplying spare parts problems | Materials quality | Machine failure | Lack of materials | | | | | | |
|
10 | Planning and scheduling | Estimation/ planning errors | Wrong time plan prediction | Inefficient planning | | | | | | | | | | | |
|
11 | Design | Delay in design | Design changes | Hurry in design | Misdesign | Nonqualified designers | | | | | | | | | |
|