Research Article
A Makespan Optimization Scheme for NP-Hard Gari Processing Job Scheduling Using Improved Genetic Algorithm
Table 6
Optimal makespan for running the GA with improved initial population.
| Population size | Execution time | Optimal makespan |
| 250.00 | 19.50 | 154.27 | 500.00 | 26.80 | 153.70 | 1000.00 | 34.73 | 152.02 | 5000.00 | 151.47 | 148.03 | 10000.00 | 270.59 | 148.01 | 20000.00 | 963.87 | 146.80 | 50000.00 | 3851.22 | 146.55 | 100000.00 | 6211.59 | 145.31 |
|
|