A Compromise Programming Model for Highway Maintenance Resources Allocation Problem
Table 4
Equipments utilization in highway maintenance with and without resource sharing (working days).
| Equipment types |
Maintenance without resource sharing |
Maintenance under āresource sharing |
Total available āequipments | Pavement | Bridge deck | Total |
| Dual-use mini vans | 4.7 | 7.4 | 12.1 | 21.7 | 25.0 | Backhoe/loaders | 3.6 | 2.4 | 6.0 | 3.8 | 11.0 | Pavement saws | 2.9 | 8.6 | 11.5 | 19.8 | 23.0 | Grinders | 2.9 | 9.7 | 12.6 | 19.8 | 26.0 | Compressors | 6.5 | 1.2 | 7.7 | 14.2 | 18.5 | Scrapers | 1.8 | 0.0 | 1.8 | 1.9 | 5.0 | Welding torch | 0.0 | 1.2 | 1.2 | 0.0 | 3.0 | Vibrating compactors | 0.0 | 8.6 | 8.6 | 9.5 | 10.0 | Cement mixers | 0.0 | 1.2 | 1.2 | 0.0 | 3.2 |
|
|