Unit production parameters.

Product 1Product 2Product 3Product 4

Production
 Minimum value10000750050008000
 Maximum value40000307502075031600
Production cost
 Facility 11122
 Facility 23235
Capacity
 Facility 120000200002000020000
 Facility 2100001000015000010000
Penalty factor 0.10.20.80.5
Delivery due date 6666
Shortage cost unit5459
Salvage cost unit0.50.511
Unit selling price86814