Breakdown of “economic” study scope at its different hierarchical levels.
| Study scope (SS) | Criterion (CR) | Oil mill housing
| Slag pit housing
| Storage depot
|
| Economy (SS4) | Cost of executing the work (CR4.1) | 0.117 | 0.089 | 0.121 | Construction timeframe (CR4.2) | 0.076 | 0.098 | 0.092 | Cost of supplies (CR4.3) | 0.054 | 0.051 | 0.065 | Cost of maintenance (CR4.4) | 0.116 | 0.198 | 0.234 | Cost of building demolition (CR4.5) | 0.075 | 0.075 | 0.000 |
|
|