Research Article

Lot-Order Assignment Applying Priority Rules for the Single-Machine Total Tardiness Scheduling with Nonnegative Time-Dependent Processing Times

Table 4

Test results of priority rules for 100 order problems.

Due date
tightness
Number of lotsEDDMOQMDDSLACKCOVERTATC
NBARDINBARDINBARDINBARDINBARDINBARDI

Sufficient150.9900.00201.00120.9970.9980.99
LooseLimited40.9800.00191.0010.9600.9100.96
Short00.5300.0030.9600.4540.97130.99

Sufficient100.9900.00191.0090.9930.9970.99
NormalLimited00.6700.0050.9700.6090.9960.98
Short00.0900.3840.9700.00120.9840.97

Sufficient00.8000.00120.9900.7780.9900.96
TightLimited00.0700.4170.9800.0080.9950.98
Short00.0600.7780.9800.0090.9930.98

Sum/average290.5800.17970.98220.53600.98460.98

Number of the best solutions found.
Average relative deviation index.