Station Black-Out Analysis with MELCOR 1.8.6 Code for Atucha 2 Nuclear Power Plant

Table 2

CNA-2 PHWR NPP versus German PWR—timing of events in an SBO.

Plant characteristicCNA-2 PHWR low pressure SBO MELCORRef. German PWR KONVOI low pressure SBO MELCOR

Core thermal power (MW) (total)21603765
Core decay power (MW) at reactor scram129.6241.9
Total volume of primary system (m3)520415
Primary system volume to core power ratio (m3/MW)0.2410.110

Event listed for CNA-2 PHWR/Event listed for PWRTime (h:m)Time (h:m)

SG dryout~2:000:57
PRZ SV failure stuck open2:31
Start of uncovery of core/moderator tank3:00/3:00~2:10/—
Total uncovery of core/moderator tank3:30/9:00~4:30/—
Gap release from fuel3:562:22
Beginning of core channel failure (PHWR), respectively Core failure and debris formation (PWR)5:162:35
Failure of surge line due to creep rupture followed by accumulator injection2:55
Fuel relocation to moderator tank bottom (PHWR)
Molten pool formation in core (PWR)
>5:30>4 h
Failure of moderator tank bottom (PHWR)/core support plate (PWR) and debris relocation to lower head11:175:02
RPV failure23:456:22