Economic Viability of Metallic Sodium-Cooled Fast Reactor Fuel in Korea
Table 4
Investment costs of SFR fuel cycle facilities.
| Capital cost | Estimated cost (kUSD) | Ratio (%) |
| Direct cost | | | Site preparation | 9,445 | Process systems | 199,194 | Main processing building | 238,668 | Site support facilities | 15,266 | Sub total | 462,573 | 50 |
| Indirect cost | | | Conceptual/final design (14%) | 64,760 | Licenses (7%) | 32,380 | General and administrative costs (5%) | 23,129 | Engineering and construction management (10%) | 46,257 | Startup and testing (20%) | 92,515 | Initial training (3%) | 13,877 | Subtotal | 272,918 | 30 |
| Contingency (25%) | 183,873 | 20 |
| Total | 919,364 | 100 |
|
|