The detailed segment composition of building construction progress.

Construction progress
First-order progress influence factor segments Second-order progress influence factor segmentsProgress score value

Site leveling progress ( )Scene investigation progress ( )
Removing obstacle progress ( )
Calibrating range, setting benchmarks, and grid progress ( )
Measuring elevation progress ( )
Calculating earthwork cut and fill engineering quantities progress ( )
Land leveling progress ( )
Field compaction progress ( )

Ground foundation progress ( )Earth excavation progress ( )
Cushion placement progress ( )
Foundation placement progress ( )
Foundation wall placement progress ( )
Base pillar, ground ring beam progress ( )
Backfilling earthwork progress ( )

Body engineering progress ( )Reinforcement engineering progress ( )
Formwork engineering progress ( )
Concrete engineering progress ( )
Masonry engineering progress ( )

Roof engineering progress ( )Clean up, leveling progress ( )
Processing insulation layer progress ( )
Waterproofing and drainage progress ( )
Setting qualified seaming progress ( )
Ventilation, exhaust progress ( )

Decoration and fitment progress ( )Groundwater seepage test of bathroom and kitchen progress ( )
Laying chisel trough and circuit pipeline progress ( )
Sealing and burying trunk progress ( )
Decoration and fitment progress of public wall ( )
Installing doors and windows progress ( )

Water, electricity, and HVAC progress ( )Water supply and sewerage progress ( )
Laying circuit progress ( )
Installing heating progress ( )
Water, heating, and electrical test progress ( )

Equipment installation progress ( )Installing elevator progress ( )
Installing fire-fighting equipment progress ( )
Installing emergency device progress ( )

Goods transportation progress ( ) Goods transportation scheme 1 progress ( )
Goods transportation scheme 2 progress ( )
Goods transportation scheme 3 progress ( )

Environmental factor progress ( )Natural environment factor progress ( )
Social environment factor progress ( )

Other factors progress ( )Construction design drawings change progress ( )
Construction machinery, materials changes progress ( )
Progress affected by weak supervision ( )
Progress affected by supply failure of the municipal system ( )
Progress affected by great political and social activities ( )