Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a Large Scale Hydropower Construction Project

Table 13

Comparison results between CP-based HPSO and standard PSO.

AlgorithmObjective function valuesConvergence iteration number Computation time (s)
(102) (106)

CP-based HPSO0.3471170.887824180.16359.47895826.3264
Standard PSO 0.3471170.887824180.16359.478912457.1683