Research Article

Multimode Resource-Constrained Multiple Project Scheduling Problem under Fuzzy Random Environment and Its Application to a Large Scale Hydropower Construction Project

Table 9

Results of the CP-based HPSO algorithm for MRCMPSP.

( )( )( )( )( )( )( )( )( )

11 03.543.54 12 08.858.85 11 018.4118.41
21 3.5412.3915.93 21 18.4135.4053.81 21 08.328.32
32 15.9318.0533.98 31 018.4118.41 32 34.3417.7052.04
41 33.987.9641.94 42 18.4126.3744.78 42 79.1213.4592.57
53 41.9439.6581.59 52 53.8128.6782.48 51 74.8715.0489.91
61 52.0410.8062.84 61 53.816.3760.18 61 18.417.2625.67
73 62.8416.2879.12 72 60.1814.6974.87 71 25.678.6734.34
81 82.489.9192.39 81 81.5910.2791.86 81 44.7817.7062.48
92 82.6616.1198.77 93 91.8648.5140.36 91 62.4820.1882.66
101 98.775.84104.61 101 92.5712.39104.96 101 89.916.3796.28
111 104.613.48108.09 111 104.9638.41143.37 111 96.289.38105.66
122 108.098.14116.23 121 104.9628.33133.29 121 105.668.14113.80
132 141.7716.11157.88 131 133.298.48141.77 132 140.3613.98154.34
141 146.1913.28159.47 141 116.2330.27146.50 141 157.884.24162.12
151 159.476.02165.49 152 113.8032.39146.19 151 154.346.36160.70
162 159.478.14167.61 161 146.508.14154.64 161 160.706.20166.90
171 154.649.20163.84 171 166.904.96171.86
181 163.844.60168.44