Project Scheduling Heuristics-Based Standard PSO for Task-Resource Assignment in Heterogeneous Grid

Table 11

A case consisting of 15 tasks.

Task no.WorkloadSuccessors no.Comm. cost

001  0  
1100002345410
2200005 8 
3500058 113 
44000069 415 
5150007 10 
6100010 5 
712000910 1020 
880001012 715 
93000012 2 
10110001113 220 
11100012 5 
1210001415 1511 
132000015 8 
14600015 2 
151300016 0 
160