Research Article
Critical Success Factors for Safety Management of High-Rise Building Construction Projects in China
Table 7
Path coefficients and significant test of the final model.
| Hypotheses | Relationship | Standardized weight | Estimate | S.E. | C.R. | value | Test result |
| H1 | CSF4 ← CSF1 | 0.104 | 0.120 | 0.178 | 0.678 | 0.498 | Reject | H2 | CSF6 ← CSF1 | 0.463 | 0.484 | 0.124 | 3.896 | | Support | H3 | CSF1 ← CSF2 | 0.393 | 0.305 | 0.080 | 3.796 | | Support | H4 | CSF3 ← CSF2 | 0.423 | 0.413 | 0.086 | 4.821 | | Support | H5 | CSF1 ← CSF3 | 0.405 | 0.323 | 0.085 | 3.800 | | Support | H6 | CSF4 ← CSF3 | 0.361 | 0.335 | 0.091 | 3.661 | | Support | H7 | CSF4 ← CSF6 | 0.302 | 0.337 | 0.130 | 2.598 | | Support | H8 | CSF4 ← CSF7 | 0.429 | 0.441 | 0.092 | 4.813 | | Support | Nonoriginal | CSF7 ← CSF2 | 0.320 | 0.283 | 0.076 | 3.727 | | Support |
|
|
|