Identification of Risk Factors Affecting PPP Waste-to-Energy Incineration Projects in China: A Multiple Case Study

Table 5

Comparative analysis of similar studies.

ProfileSong et al. [4]Xu et al. [23]The present study

Research methodsExpert interview and site investigationLiterature review and multiple cases studied using content analysisLiterature review and multiple cases studied using content analysis
Number of cases studied61435
Time range of eventsBefore 20082002–20122001–2016, with 80% after 2012
Criteria for case selectionAll cases in operationAll cases in operationAbout 2/3 of cases in operation
Risk factors identified10 key risk factors5 critical risk factors18 risk factors with 5 high-frequency risk factors
Critical risk factors (high-frequency risk factors) discussedGovernment decision-making riskInsufficient waste supplyPublic opposition risk
Government credit riskEnvironmental riskEnvironmental pollution risk
Legal and policy riskEntry of nonlicensed wasteGovernment decision-making risk
Technical riskLack of supporting infrastructureDefective legal and regulatory system
Contract change riskPayment riskMSW supply risk
Environment risk
Public opposition risk
MSW supply risk