A BIM-Based Study on the Comprehensive Benefit Analysis for Prefabricated Building Projects in China

Table 6

Economic benefit values on main days in the project.

Construction period (day)Economic benefits (¥/m2)
Resource-savingTime-savingPolicy subsidiesComprehensive economic benefits

12.0321.3750.5073.90
104.0642.7452.6099.40
206.0964.1156.90127.10
2912.1285.4862.30159.90
3915.15106.8563.10185.10
5217.18128.2264.20209.60
6122.21149.5965.20237.00
7125.24170.9666.40262.60
7429.27192.3366.70288.30
7934.30213.7067.80315.80
8538.33235.0769.40342.80
9241.36256.4470.90368.70
10342.69297.8171.00411.50
11543.42332.1872.40448.00
12444.75343.5573.10461.40
13545.48361.9274.60482.00
14346.51392.2975.30514.10
15747.54425.6676.10549.30
16448.57463.0377.20588.80
17949.60497.4078.10625.10
18951.62521.7779.20652.60
20752.65552.9580.10685.71
23752.65552.9589.00694.61
26652.65552.9595.00700.61
26752.52552.95133.00738.48