A BIM-Based Study on the Comprehensive Benefit Analysis for Prefabricated Building Projects in China
Table 6
Economic benefit values on main days in the project.
| Construction period (day) | Economic benefits (¥/m2) | Resource-saving | Time-saving | Policy subsidies | Comprehensive economic benefits |
| 1 | 2.03 | 21.37 | 50.50 | 73.90 | 10 | 4.06 | 42.74 | 52.60 | 99.40 | 20 | 6.09 | 64.11 | 56.90 | 127.10 | 29 | 12.12 | 85.48 | 62.30 | 159.90 | 39 | 15.15 | 106.85 | 63.10 | 185.10 | 52 | 17.18 | 128.22 | 64.20 | 209.60 | 61 | 22.21 | 149.59 | 65.20 | 237.00 | 71 | 25.24 | 170.96 | 66.40 | 262.60 | 74 | 29.27 | 192.33 | 66.70 | 288.30 | 79 | 34.30 | 213.70 | 67.80 | 315.80 | 85 | 38.33 | 235.07 | 69.40 | 342.80 | 92 | 41.36 | 256.44 | 70.90 | 368.70 | 103 | 42.69 | 297.81 | 71.00 | 411.50 | 115 | 43.42 | 332.18 | 72.40 | 448.00 | 124 | 44.75 | 343.55 | 73.10 | 461.40 | 135 | 45.48 | 361.92 | 74.60 | 482.00 | 143 | 46.51 | 392.29 | 75.30 | 514.10 | 157 | 47.54 | 425.66 | 76.10 | 549.30 | 164 | 48.57 | 463.03 | 77.20 | 588.80 | 179 | 49.60 | 497.40 | 78.10 | 625.10 | 189 | 51.62 | 521.77 | 79.20 | 652.60 | 207 | 52.65 | 552.95 | 80.10 | 685.71 | 237 | 52.65 | 552.95 | 89.00 | 694.61 | 266 | 52.65 | 552.95 | 95.00 | 700.61 | 267 | 52.52 | 552.95 | 133.00 | 738.48 |
|
|