Implementation of Process-Based and Data-Driven Models for Early Prediction of Construction Time
Table 8
Comparison of the accuracy of the five new hybrid models using 10-fold cross-validation.
| Type of the predictive hybrid model | MAPE (%) | R2 (%) | Coefficient of correlation between actual and predicted target values |
| BTC-SVM | 3.9 | 91.63 | 0.958 | BTC-LR | 4.5 | 89.39 | 0.950 | BTC-RBFNN | 4.31 | 90.65 | 0.953 | BTC-MLPNN | 4.28 | 89.91 | 0.948 | BTC-GRNN | 3.34 | 93.17 | 0.966 |
|
|