Analysis on Deformation and Stress Characteristics of a Multibraced Pit-in-Pit Excavation in a Subway Transfer Station

Table 3

Construction sequence for the finite element analysis.

StageConstruction detailsDay

Before excavation
IConstruction of diaphragm wall2018/08/01

External excavation
II-1Excavation to 1.9 m below ground surface
II-2Installing prop 1 at 1.4 m below ground surface10/23
II-3Excavation on the east-west sides to 8.1 m below ground surface
II-4Install prop 2 on the east-west side at 7.6 m below ground surface
II-5Excavation on the east-west sides to 13.7 m below ground surface
II-6Installing prop 3 on the east-west side at 13.2 m below ground surface
II-7Excavation on the east-west sides to 16.9 m below ground surface (reaching the bottom of outer excavation)
III-1Excavation at the intersection to 8.1 m below ground surface
III-2Installing the prop 2 at the intersection at 7.6 m below ground surface12/10
III-3Excavation at the intersection to 13.7 m below ground surface
III-4Installing the prop 3 at the intersection at 13.2 m below ground surface2019/01/20
III-5Excavation at the intersection to 16.9 m below ground surface (reaching the bottom of outer excavation)02/05

Internal excavation
IV-1Excavation at the intersection to 18.2 m below ground surface
IV-2Installing the prop 4 at the intersection at 17.7 m below ground surface02/15
IV-3Excavation at the intersection to 22.4 m below ground surface
IV-4Installing the prop 5 at the intersection at 21.9 m below ground surface03/13
IV-5Excavation at the intersection to 25.8 m below ground surface (reaching the bottom of inner excavation)04/10