Research Article

Model and Algorithm for Dependent Activity Schedule Optimization Combining with BIM

Table 4

Time distribution of material provided by vendors.

Reliability record (actual date-agreed date)FrequencyCumulative frequencyPercentage frequency (%)Percentage cumulative frequency (%)

−30000
−2222222
−1131133
0363467
1282289
21911100
3090100