Research Article

The Prediction of Pile Foundation Buried Depth Based on BP Neural Network Optimized by Quantum Particle Swarm Optimization

Table 1

43 groups of data for training.

No.Pile numberBorehole numberX-coordinateY-coordinateZ-coordinateh1 (m)h2 (m)h3 (m)h4 (m)H (m)

13K4211.7510171.288031.93000.4012.603.806.6023.40
212K4332.2510174.288031.70000.7012.104.505.9023.20
327K4459.6510174.288031.96001.3012.603.106.7023.70
441K4582.4510175.638031.92000.8014.202.706.9024.60
551K4691.7000164.938031.97000.9012.703.307.6024.50
3915K6653.0730246.524031.74001.4012.302.706.8023.20
40160K5612.7330204.027031.61001.309.005.507.6023.40
41151K5736.2730204.941031.59001.3011.903.007.1023.30
42148K5853.0730203.541031.86001.2013.302.106.8023.40
43139K5973.5230204.941031.94001.304.509.907.7023.40