Research Article
Optimization of Flow Shop Scheduling in Precast Concrete Component Production via Mixed-Integer Linear Programming
Table 2
Completion time of each process based on the FSSM.
| Component production sequence | Process completion time (h) | Delay time (h) | Restoring time (h) | Mold assembling | Reinforcement setting | Concrete casting | Curing | Mold removal | Finishing/repairing |
| 4 | 0.3 | 0.7 | 1.2 | 24 | 24.4 | 25.4 | — | 2.6 | 2 | 2 | 4 | 6 | 24 | 25.9 | 28.4 | 0.4 | — | 6 | 3.5 | 5.6 | 7.5 | 24 | 27.7 | 29.2 | — | 2.8 | 1 | 4.5 | 6.4 | 8.7 | 24 | 29.2 | 29.7 | 1.7 | — | 3 | 4.9 | 6.9 | 9.3 | 24 | 29.7 | 29.7 | 1.7 | — | 5 | 6.4 | 24.7 | 25.9 | 48 | 49.5 | 51∗ | — | 1 | Total delay time (h) | 3.8 | — | Total restoring time (h) | — | 6.4 |
|
|
∗Orders complete time.
|