Optimization of Flow Shop Scheduling in Precast Concrete Component Production via Mixed-Integer Linear Programming

Table 4

Operating time and delivery deadline of each process for 10 components.

Component numberProcess operation time (h)Delivery period (h)
Mold assemblingReinforcement settingConcrete castingMold removalFinishing/repairing

110.81.21.50.532
21.7221.52.532
30.40.50.60.5032
40.30.40.50.4148
51.51.81.21.51.548
61.51.61.51.80.848
710.81.21.50.552
81.7221.52.552
90.30.40.50.4156
101.51.81.21.51.556