Optimization of Flow Shop Scheduling in Precast Concrete Component Production via Mixed-Integer Linear Programming

Table 7

Overtime plan for scheme (2).

Component production sequenceProcess operation time (h)
Mold assemblingReinforcement settingConcrete castingMold removalFinishing/repairing

300000
400000
200000
5000.800
100000
600.62.300
701.43.50.70
800000
900000
1000000
Overtime of each process (h)02.06.60.70
Total overtime (h)9.3