Future Long-Baseline Neutrino Facilities and Detectors
Table 3
Beam conditions and power possible during the Project-X phase and further upgrades to the 8 GeV performance. An accumulator ring at 8 GeV could be used to improve the duty factor.
Accelerator stage
Energy
Current
Duty factor
Power available
Continuous wave linac
3 GeV
1 mA
Continuous wave
3000 kW
Pulsed linac
8 GeV
43
A
4.33 ms/0.1 sec
350 kW
8 GeV upgrade
8 GeV
500
A
6.67 ms/0.066 sec
4000 kW
Main injector
60 GeV
35
A
9.5
S/0.7 sec
2100 kW
Main injector
120 GeV
19
A
9.5
S/1.3 sec