Construction Time of Three Wall Types Made of Locally Sourced Materials: A Comparative Study
Table 13
Time necessary to make compacted clay walls.
| ā | Formwork | Loading, transport, and unloading for formwork | Charge levelling | Compaction | Total time | Total time |
| ā | m-h/m3 | m-h/m2 | Ground floor | 3.10 | 2.88 | 0.72 | 0.95 | 7.65 | 2.295 | 1st floor | 3.38 | 2.92 | 0.75 | 0.95 | 8.00 | 2.40 |
|
|
Source: own study.
|