Research Article

New Chemical Grouting Materials and Rapid Construction Technology for Inclined Shaft Penetrating Drift-Sand Layer in Coal Mine

Table 4

Main technical parameters of construction chemical grouting.

CategoryTwo-component ratioWidth of the smallest crack (mm)Setting time (min)Resin viscosity (MPa·s)Catalyst viscosity (MPa·s)

MGS1 : 1∼1 : 20.0110∼25015050∼80