STR-mSTR-1STR-2STR-3STR-4STR-5STR-6

Surface course4 cm5 cm4 cm4 cm5 cm4 cm4 cm
AC-13AC-16SMA-13AC-13AC-16AC-13SMA-13
5 cm7 cm6 cm6 cm7 cm6 cm6 cm
AC-20AC-20AC-20AC-20AC-20AC-20AC-20
7 cm8 cm8 cm8 cm8 cm
AC-25AC-25AC-25AC-25AC-25

Base course34 cm cement-treated sand gravel35 cm cement-treated sand gravel36 cm cement-treated sand gravel14 cm ATB3010 cm ATB2512 cm ATB2512 cm ATB25
18 cm natural sand gravel26 cm natural sand gravel20 cm natural sand gravel26 cm graded macadam36 cm cement-treated sand gravel20 cm cement-treated sand gravel18 cm cement-treated sand gravel
20 cm natural sand gravel26 cm natural sand gravelNatural sand gravel

Total depth (cm)68737458787668