| | PI | min. | max. |
| (I) Asset assessment phase (6 months)/programme development costs | | | |
| Personnel costs of the scientists | 29,668 € | 26,701 € | 32,635 € | Nonpersonnel costs | 5,950 € | 2,975 € | 8,925 € | Total | 35,618 € | 29,676 € | 41,560 € |
| (II) Programme design phase (6 months)/programme development costs | | | |
| Personnel costs of the scientists, the stakeholders and representatives of the target group | 45,139 € | 40,626 € | 49,653 € | Nonpersonnel costs | 3,650 € | 1,825 € | 5,475 € | Total | 48,789 € | 42,451 € | 55,128 € |
| (III) Programme implementation phase (12 months)/programme implementation costs | | | |
| Implementation costs: personnel costs of the scientists, the stakeholders and of some members of the target group | 33,947 € | 30,552 € | 37,341 € | Implementation costs: nonpersonnel costs | 2,800 € | 1,400 € | 4,200 € | Recruitment costs: costs of marketing and information | 1,075 € | 537 € | 1,612 € | Recruitment costs: costs of pilot workout and health seminar | 2,592 € | 2,141 € | 3,043 € | Programme costs (actual costs) | 3,532 € | 2,846 € | 4,218 € | Programme costs (imputed costs) | 8,253 € | 6,421 € | 10,491 € | Total | | | | Payers perspective | 43,946 € | 37,446 € | 50,414 € | Societal perspective | 48,666 € | 41,021 € | 56,687 € |
| All phases (I–III) | | | |
| Payer’s perspective | 128.353 € | 109,603 € | 147,102 € | Societal perspective | 133,074 € | 113,178 € | 153,375 € |
|
|