A Cost Optimization Model for Multiresource Leveling Problem without Project Duration Constraint
Table 1
Data about the situation of project.
| ID | Duration | Daily resource demand | | | | R1 | R2 | R3 |
| A | 2 | 2 | 1 | 0 | 1 | 6 | B, K | B | 3 | 4 | 1 | 1 | 3 | 8 | C | C | 2 | 2 | 1 | 0 | 6 | 11 | D | D | 3 | 1 | 1 | 0 | 8 | 13 | E | E | 3 | 4 | 2 | 0 | 11 | 16 | F | F | 2 | 6 | 3 | 0 | 14 | 19 | | G | 4 | 4 | 1 | 1 | 1 | 9 | H | H | 3 | 5 | 0 | 2 | 5 | 13 | E | K | 2 | 2 | 1 | 0 | 3 | 13 | L | L | 4 | 2 | 0 | 1 | 5 | 15 | F |
|
|