Colored Petri Net-Based Verification and Improvement of Time-Sensitive Single-Unit Manufacturing for the Soil Preparation Instrument of Space Missions

Table 3

Manufacturing process and required resources.

IDTask nameDuration (days)PredecessorResource name (number)

11. CPN0005100
21.1. Initial design phase CPN000540Designer (2)
31.2. PART003038
41.2.1. Detail specification PART003052Designer (2)
51.2.2. Purchase PART0030304
61.2.3. Inspection PART003035Inspector (1)
71.3. CPN001234
81.3.1. Design & cost CPN001272Designer (2)
91.3.2. Purchase PART0031218
101.3.3. Purchase PART00358
111.3.4. Inspection PART003119Inspector (1)
121.3.5. Inspection PART0032310Inspector (1)
131.3.6. subassembly CPN0012211, 12Operator (1)
141.3.7. Inspection CPN0012313Inspector (1)
151.4. PART003323
161.4.1. Detail specification PART003352Designer (2)
171.4.2. Purchase PART00331516
181.4.3 Inspection PART003337Inspector (1)
191.5. PART003421
201.5.1. Design & test CPN003482Designer (2)
211.5.2. Manufacturing PART00341020Operator (2)
221.5.3. Inspection PART0034321Inspector
231.6. Assembly CPN0005816, 14, 18, 22Operator (4)
241.7. Test CPN0005723Inspector (4)
261.8. Inspection CPN0005724Inspector