Table 3

Parameters of the boreholes.

Borehole memberBorehole locationBorehole depth (m)Borehole height (m)

1#, 3#, 5#Upper row1000.8 m from the roof
2#, 4#, 6#Lower row1001.8 m from the roof
7#, 9#Upper row700.8 m from the roof
8#, 10#Lower row701.8 m from the roof
11#, 13#, 15#, 17#, 19#, 21#Upper row600.8 m from the roof
12#, 14#, 16#, 18#, 20#, 22#Lower row601.8 m from the roof