Observed Performance and FEM-Based Parametric Analysis of a Top-Down Deep Excavation in Soil-Rock Composite Stratum
Table 1
Summary of the main construction activities.
| Stage | Construction activities | Duration (days) |
| 1 | Excavate to top slab, construct columns and top slab, and backfill and restore traffic | 78 | 2 | Construct end-suspended piles, excavate to 2 m BGS | 59 | 3 | Install ground anchors YMG1 and YMG2, apply prestress of 200 kN | 17 | 4 | Excavate to 5 m BGS | 14 | 5 | Construct temporary support | 9 | 6 | Excavate to 7 m BGS | 12 | 7 | Install ground anchors YMG3, apply prestress of 100 kN | 19 | 8 | Excavate to 8 m BGS | 22 | 9 | Install ground anchors YMG4, apply prestress of 310 kN | 16 | 10 | Excavate to 9.5 m BGS | 13 | 11 | Install ground anchors MG1 | 7 | 12 | Excavate to 12 m BGS | 15 | 13 | Install ground anchors MG2 | 23 | 14 | Excavate to 13.5 m BGS, cast middle slab | 17 | 15 | Install ground anchors MG3 | 26 | 16 | Excavate to 15.5 m BGS | 11 | 17 | Install ground anchors MG4 | 18 | 18 | Excavate to 17.5 m BGS | 29 | 19 | Install ground anchors MG5 | 21 | 20 | Excavate to 20 m BGS | 10 | 21 | Cast base slab | 19 |
|
|