Observed Performance and FEM-Based Parametric Analysis of a Top-Down Deep Excavation in Soil-Rock Composite Stratum

Table 1

Summary of the main construction activities.

StageConstruction activitiesDuration (days)

1Excavate to top slab, construct columns and top slab, and backfill and restore traffic78
2Construct end-suspended piles, excavate to 2 m BGS59
3Install ground anchors YMG1 and YMG2, apply prestress of 200 kN17
4Excavate to 5 m BGS14
5Construct temporary support9
6Excavate to 7 m BGS12
7Install ground anchors YMG3, apply prestress of 100 kN19
8Excavate to 8 m BGS22
9Install ground anchors YMG4, apply prestress of 310 kN16
10Excavate to 9.5 m BGS13
11Install ground anchors MG17
12Excavate to 12 m BGS15
13Install ground anchors MG223
14Excavate to 13.5 m BGS, cast middle slab17
15Install ground anchors MG326
16Excavate to 15.5 m BGS11
17Install ground anchors MG418
18Excavate to 17.5 m BGS29
19Install ground anchors MG521
20Excavate to 20 m BGS10
21Cast base slab19