Research Article
3D Point Cloud Data Basis Shape Management for Assembly of Modularized Large and Complicated Marine Structures
Table 2
Cost burden examples of existing methods for the leg block assembly.
| | Dimensions | Weight (abt.) | Crane capacity | Additional cost caused by construction delay in the dock | Crane | Man-hour | Construction delay | Additional cost |
| Case 1 | 65 m × 32 m | 7,000 ton | 9,000 ton | 14 hours | 37 m/h × 14 h | 1.5 days | 268,000 US dollars | Case 2 | 37 m × 34 m | 4,500 ton | 9,000 ton | 10 hours | 37 m/h × 10 h | 1 day | 250,000 US dollars | Case 3 | 37 m × 34 m | 4,500 ton | 9,000 ton | 12 hours | 37 m/h × 12 h | 1 day | 223,000 US dollars |
|
|