3D Point Cloud Data Basis Shape Management for Assembly of Modularized Large and Complicated Marine Structures

Table 2

Cost burden examples of existing methods for the leg block assembly.

DimensionsWeight (abt.)Crane capacityAdditional cost caused by construction delay in the dock
CraneMan-hourConstruction delayAdditional cost

Case  165 m × 32 m7,000 ton9,000 ton14 hours37 m/h × 14 h1.5 days268,000
US dollars
Case  237 m × 34 m4,500 ton9,000 ton10 hours37 m/h × 10 h1 day250,000
US dollars
Case  337 m × 34 m4,500 ton9,000 ton12 hours37 m/h × 12 h1 day223,000
US dollars