Uncertainty Analysis of Energy Production for a 3 × 50 MW AC Photovoltaic Project Based on Solar Resources
Table 11
Confidence limits for the PV layout of PV plant 1- and 10-year periods, without power degradation.
| Probability of exceedance (%) | 1 year | 10 years | Net energy output (MWh/annum) | Capacity factor (%/annum) | Net energy output (MWh/annum) | Capacity factor (%/annum) |
| 99 | 86,683 | 15.3% | 88,146 | 15.5% | 90 | 97,700 | 17.2% | 98,506 | 17.4% | 75 | 104,101 | 18.3% | 104,525 | 18.4% | 60 | 108,542 | 19.1% | 108,701 | 19.1% | 50 | 111,213 | 19.6% | 111,213 | 19.6% | 25 | 118,325 | 20.8% | 117,900 | 20.8% | Total | 104,761 | 18.4% | 104,832 | 18.5% |
|
|