Multiobjective Transmission Network Planning considering the Uncertainty and Correlation of Wind Power
Table 4
Final planning scheme of the real test system.
| Desirable level | Investment cost (M$) | Amount of line overload (MW) | Network losses cost (M$) |
| 0.2 | 1 | 1 | 18390.9 | 30.7138 | 1663.62 | 0.4 | 1 | 1 | 17740.4 | 68.3243 | 1719.06 | 0.6 | 1 | 1 | 12395 | 33.4318 | 1956.2 |
|
|