Analyzing Integrated Cost-Schedule Risk for Complex Product Systems R&D Projects
Table 4
Integrated probability distribution of total cost and duration
.
| Total cost | Total duration | 53 | 56 | ⋯ | 74 | 77 | ⋯ | 107 | 110 |
| 5300 | 0.000 | 0.000 | ⋯ | 0.000 | 0.000 | ⋯ | 0.001 | 0.001 | 5600 | 0.000 | 0.001 | ⋯ | 0.003 | 0.003 | ⋯ | 0.006 | 0.006 | ⋯ | ⋯ | ⋯ | ⋯ | ⋯ | ⋯ | ⋯ | ⋯ | ⋯ | 7700 | 0.000 | 0.001 | ⋯ | 0.135 | 0.210 | ⋯ | 0.593 | 0.593 | 8000 | 0.000 | 0.001 | ⋯ | 0.139 | 0.219 | ⋯ | 0.715 | 0.715 | ⋯ | ⋯ | ⋯ | ⋯ | ⋯ | ⋯ | ⋯ | ⋯ | ⋯ | 10700 | 0.000 | 0.001 | ⋯ | 0.139 | 0.225 | ⋯ | 0.999 | 0.999 | 11000 | 0.000 | 0.001 | ⋯ | 0.139 | 0.225 | ⋯ | 1.000 | 1.000 |
|
|